Skip to main content

Chaining tasks with dependencies

Written by Ivan Soldo

When creating a one-time task, use Wait for another task to finish to make it wait for another task. This control is unavailable for recurring tasks. When Marktic completes the earlier task through its workflow, it triggers the dependent task to start. Manually changing the earlier task’s status does not trigger the same process.

A task can wait on one other task, a single link rather than a list. To build a longer sequence, chain them: A, then B depends on A, then C depends on B.

When it's useful

The point of a dependency is when a task needs what an earlier one produced before it can start. For example:

  • Run keyword research, build topic clusters from the results, then write the pages around those clusters

  • Gather product details into a database, then build the site pages that pull from it

  • Run an in-depth competitor analysis, then plan campaigns to run against those competitors

In each case, the later task needs the results of the earlier one. A dependency sets the intended order of work.

When it isn't

If two tasks don't actually need each other, leave them independent. A chain means a failure early on stops everything after it.

If a dependent task never runs

First, check the task it depends on. If that task is still running, waiting for your input, or has failed, the dependent task may still be waiting.

If the earlier task is complete but the dependent task hasn’t started, contact support so engineering can investigate. Share the task links if available. You don’t need to recreate the tasks or remove the dependency first.

Did this answer your question?